2021 Street Maintenance Overlay
A
A
2021 Street Maintenance Overlay
Notify Us
Report Issues & Submit Questions
Subscribe
Receive Updates on Current Projects
These Projects Include
1.5" mill and overlay
Partial curb replacement
Water main replacement (
Highland Area neighborhood only
)
Repaving (
Highland Area and Frontier Court only
)
Contacts
Project Manager:
Logan Vlasaty
Highland Forest Area (Phase 1) Inspector:
Jason Malecha
, Bolton and Menk, Phone (507) 581-2256
All Other Areas (Phases 2-5) Inspector:
Tim Zahratka
, Phone (612) 619-5892
Highland Forest Area (Phase 1) Contractor:
McNamara Contracting
All Other Areas (Red Oak, Vista View, Heather Hills Drive, and Frontier Court) Contractor:
Minnesota Paving and Materials
Updates
See map below for reference
Highland Forest Area:
~ Phase 1
May - June: paving final layer of asphalt
~
Phase 2
May - June: paving final layer of asphalt
~ Phase 3
completed
Completed phases:
Red Oak Area
Vista View Area
Heather Hills Area
Frontier Court
Highland Forest Area Map
View larger map
2022 Street Improvement Projects
2021 Street Maintenance Overlay
Cliff Road Trail
Twin Lakes Proposed Improvements
Arrow Left
Arrow Right
[]
Slideshow Left Arrow
Slideshow Right Arrow