Twin Lakes Proposed Improvements

Project Description

As you may have noticed, No-Wake zones have been enforced at Crystal Lake to prevent degradation of the shoreline. In addition, the Twin Lakes (North and South, part of the same chain of critical water bodies as Crystal Lake) have been known to be prone to flooding. To address these issues the City has developed a set of proposed improvements including: 

  1. Regional Pond Expansion
  2. New South Twin Lake Outlet
  3. Crystal Lake Outlet Modifications

Click on the below image to explore details on the proposed improvements and to see a snapshot of the overall production schedule. 

Contacts

Updates 

September 20 - 26

Click the Construction Update (PDF) for a printable pdf version of this information.

1. Regional Pond 

  • No active construction anticipated in the project area. The contractor will be completing final cleanup items on the project as needed.

2. South Twin Outlet 

See below for more information about about traffic control and access closure.

  • Contractor has paved the roadway.  They will be striping the roadway, seeding the boulevards, and completing the remaining cleanup items.  The roadway is anticipated to be open later in the week.
  • During the week of September 27 - October 3, major construction is anticipated to be completed with the roadway open back up to traffic.

3. Crystal Lake Outlet

  • Contractor will be completing tree removals and starting to work actively at the site.  A portion of the boat launch parking lot will be utilized by the contractor as a staging and material storage area.
  • During the week of September 27 - October 3, the contractor will be replacing the existing outlet structure and utilizing a portion of the boat launch parking lot for material storage and staging.

South Twin Outlet Traffic Control and Access Closure

Click here or on image below for more information

What:  Traffic control on Southcross Drive and closure of the access of western Carriage Lane and Southcross Drive (as shown in image below)

When:  Starting around August 2, 2021 (tentatively) and lasting approximately eight (8) weeks.

Why:  The City’s contractor will be working in Southcross Drive installing new storm sewer pipes that will connect with the new South Twin Lake outlet structure located on the north side of the lake.   For their safety, the southern lanes of Southcross must be closed and traffic shifted to the northern lanes.   The western Carriage Lane access to Southcross Drive must be closed for the duration of this work because the traffic shift occurs at the median opening and for driver safety, the access must be closed.

Neighborhood Access Closure Map


TWIN LAKES IMPROVEMENTS Opens in new window