Southwest Area (2020)

Overview

Rehabilitation work consists of replacing the top 2" of pavement and spot replacement of curbs. The following are the areas included in this project:

~ Loop Road North~ Loop Road South
~ Marcia Ann Lane~ Brown Lane
~ Omeara Court~ 152nd St. West
~ Circle High Drive


Contacts

Links

Updates:

See phasing map below for reference

Updates for the week of May 25-30, 2020

See updates below by phase.  Click the Weekly Construction Update (PDF) for a printable pdf version with additional information.

Phase 1

  • Milling and paving asphalt driveway apron transitions for the overlay
  • Pave 2” overlay with asphalt curb on Circle High Drive late in the week
  • May start paving 2” overlay on other streets at the end of the week if time permits
Southwest Area Phasing Map