Highland View Area

GovDelivery envelope logo Opens in new windowSubscribe to email updates

Overview

Reconstruction (northern half) consists of complete curb and gutter replacement, roadway reconstruction, water main replacement, storm sewer repairs and upgrades, and sanitary sewer repairs. Reclamation (southern half) consists of replacing all pavement, repairing and/or upgrading storm sewers and sanitary sewers, and spot replacement of curbs.

Notify Us

Click on Notify Us above to tell us about anything on your property or street related to the current projects.

Contacts

Links

Updates

Click on your street segment on the map below or see below for updates.

September 19, 2019

  • Phase 2 (Horizon Lane, Circle, and Road): Paving the first layer of asphalt was once again delayed by rain. Paving is scheduled early in the week of September 23, 2019.
  • Phase 3 (Reclamation Areas): A pedestrian ramp will be re-installed at 121st St and Connely Dr. in the next couple of weeks. Final layer of paving is scheduled for mid October 2019.
  • Phase 4 (Highland View Avenue, Lane, and Circle): Water main replacement was postponed to September 23, 2019. Paving the first layer of asphalt is on schedule for mid to late October 2019.

September 13, 2019

  • Phase 2 (Horizon Lane, Circle, and Road): Paving the first layer of asphalt has been postponed to September 18, 2019 due to weather. Paving asphalt driveways and boulevard restoration is scheduled to take place shortly after paving and is expected to take about 10 days.
  • Phase 3 (Reclamation Areas): Boulevard grading and seeding is expected to take place within the next couple weeks, weather permitting.
  • Phase 4 (Highland View Avenue, Lane, and Circle): Water main replacement is scheduled to start September 17, 2019. Homes are scheduled to be switched back to the new water main starting late in the week of September 23, 2019.